Mass Project Recalculate Analysis
Mass Processing in Advanced Project ManagementThere are several mass processing options that allow you to perform a process against multiple selected projects. With each menu option, you can trigger the relevant process to run immediately, or you can add it to a schedule. |
Use the Mass Project Recalculate Analysis process to run the recalculate analysis for multiple projects. See also: Running Recalculate Analysis.
To schedule Mass Project Recalculate Analysis:
-
Navigate to Mass Project Recalculate Analysis (Advanced Project Management > General Operations > Mass Project Recalculate Analysis).
-
Optionally filter by Project Id, Project Description, Project Start Date, Project End Date, and Recalculate Mode on the Filter card.
-
Set the schedule on the Advanced card.
Scheduling Process Set
To set the process schedule for any of the mass processes, fill in the details on the Advanced card in the application:
-
Select a Schedule. Select Now if you want to run the process immediately.
To schedule the process for a different time, select a different Schedule from the drop-down list. Schedules are maintained in the System Agent Maintenance screen in Standard Kinetic.
-
For a scheduled process, select Recurring for the task to recur. This check box is available for any Schedule other than Now.
For further information on Schedules, refer to the standard Kinetic Help topics System Agent Maintenance > Schedules. -
-
Select Process
.